Rehabilitation of Devon Road
Federal contribution
$86,109
Federal share45%
of $191.4K total eligible cost; the rest comes from other partners.
Schedule
Announced and approvedJun 5, 2009
20102011
Built
- Program
- Building Canada Fund - Communities Component Top Up
- Ultimate recipient
- Local Roads Board of Devon Landing
- Construction start
- Aug 19, 2009(actual)
- Construction end
- Dec 31, 2010(actual)
Also in Chapleau