Back to projects

Restoration and Upgrades to the Pickering Museum Village

Pickering, Ontario

completeCultureCC
Federal contribution
$292,999
Federal share33%

of $879.0K total eligible cost; the rest comes from other partners.

Schedule

Announced and approvedFeb 13, 2009
2009201020112012
Built
Program
Building Canada Fund - Communities Component
Ultimate recipient
City of Pickering
Construction start
Jun 1, 2010(actual)
Construction end
Jun 20, 2012(actual)

Against the original forecast

  • Construction end7 weeks lateforecast Apr 30, 2012