Construction of the Teeswater-Formosa Sanitary Sewer Collection and Treatment System
Federal contribution
$6.5M
$6,533,333
Federal share33%
of $19.6M total eligible cost; the rest comes from other partners.
Schedule
Announced and approvedFeb 13, 2009
2009201120132015
Built
- Program
- Building Canada Fund - Communities Component
- Ultimate recipient
- Municipality of South Bruce
- Construction start
- Oct 27, 2009(actual)
- Construction end
- Dec 31, 2014(actual)
Against the original forecast
- Construction start8 weeks lateforecast Sep 1, 2009
- Construction end13 months lateforecast Dec 1, 2013