Teeswater Library Renovation and Accessibility
Federal contribution
$115,000
Federal share33%
of $345.0K total eligible cost; the rest comes from other partners.
Schedule
AnnouncedJun 5, 2009
ApprovedAug 17, 2009
2010
Built
Approved 2 months after the announcement.
- Program
- Infrastructure Stimulus Fund
- Ultimate recipient
- Municipality of South Bruce
- Construction start
- Nov 2, 2009(actual)
- Construction end
- Jul 31, 2010(actual)
Against the original forecast
- Construction start7 weeks lateforecast Sep 17, 2009
- Construction end2 months earlyforecast Sep 30, 2010