Replacement of Watermains and Storm Sewer Upgrades on Fifth Street West
Federal contribution
$1.1M
$1,068,996
Federal share33%
of $3.3M total eligible cost; the rest comes from other partners.
Schedule
Announced and approvedFeb 13, 2009
20102011
Built
- Program
- Building Canada Fund - Communities Component
- Ultimate recipient
- Town of Cochrane
- Construction start
- Jul 1, 2009(actual)
- Construction end
- Oct 13, 2011(actual)
Against the original forecast
- Construction end11 months lateforecast Oct 29, 2010
Also in Cochrane
Amounts are federal dollars committed, not spent to date. Status is inferred from the dates above, not reported by the source. Project 24670 in the federal list. How to read these figures.