Genier Road Resurfacing

Cochrane, Ontario

completeHighways and RoadsISF
Federal contribution
$1.2M
$1,187,600
Federal share33%

of $3.6M total eligible cost; the rest comes from other partners.

Schedule

AnnouncedJun 5, 2009
ApprovedAug 17, 2009
20102011
Built

Approved 2 months after the announcement.

Program
Infrastructure Stimulus Fund
Ultimate recipient
Town of Cochrane
Construction start
Sep 28, 2009(actual)
Construction end
Jun 30, 2011(actual)