Expansion of the Puslinch Multi - Use Recreational Facility
Federal contribution
$716,328
Federal share33%
of $2.1M total eligible cost; the rest comes from other partners.
Schedule
Announced and approvedFeb 13, 2009
20102011
Built
- Program
- Building Canada Fund - Communities Component
- Ultimate recipient
- Township of Puslinch
- Construction start
- Feb 13, 2009(actual)
- Construction end
- Sep 12, 2011(actual)
Against the original forecast
- Construction end7 months earlyforecast Mar 31, 2012