Rehabilitation of the Municipality of Wawa Air Terminal
Federal contribution
$24,566
Federal share33%
of $73.7K total eligible cost; the rest comes from other partners.
Schedule
Announced and approvedFeb 13, 2009
Built
- Program
- Building Canada Fund - Communities Component
- Ultimate recipient
- Municipality of Wawa
- Construction start
- Sep 21, 2009(actual)
- Construction end
- Oct 15, 2009(actual)
Also in Wawa
Amounts are federal dollars committed, not spent to date. Status is inferred from the dates above, not reported by the source. Project 24711 in the federal list. How to read these figures.