Whitesands Creek Rehabilitation

Wawa, Ontario

completeOtherNIF
Federal contribution
$248,800
Federal share100%

of $248.8K total eligible cost; the rest comes from other partners.

Schedule

Announced and approvedJul 24, 2024
202420252026
Built

Approved 14 months before the announcement.

Program
Natural Infrastructure Fund
Ultimate recipient
Michipicoten First Nation
Construction start
Aug 6, 2024(actual)
Construction end
Dec 19, 2025(actual)

Against the original forecast

  • Construction start4 months lateforecast Apr 1, 2024

Also in Wawa

Amounts are federal dollars committed, not spent to date. Status is inferred from the dates above, not reported by the source. Project 65892 in the federal list. How to read these figures.