Wawa Airport Airside Pavement Rehabilitation
Federal contribution
$161,842
Federal share20%
of $801.4K total eligible cost; the rest comes from other partners.
Schedule
AnnouncedJun 5, 2009
ApprovedAug 17, 2009
2010
Built
Approved 2 months after the announcement.
- Program
- Infrastructure Stimulus Fund
- Ultimate recipient
- Municipality of Wawa
- Construction start
- Aug 25, 2010(actual)
- Construction end
- Sep 30, 2010(actual)
Against the original forecast
- Construction start7 weeks lateforecast Jul 5, 2010
- Construction end2 weeks lateforecast Sep 15, 2010