Rehabilitation of Oil Springs Line
Federal contribution
$80,000
Federal share33%
of $240.0K total eligible cost; the rest comes from other partners.
Schedule
Announced and approvedFeb 13, 2009
2010
Built
- Program
- Building Canada Fund - Communities Component
- Ultimate recipient
- Township of Enniskillen
- Construction start
- Aug 10, 2009(actual)
- Construction end
- Jul 23, 2010(actual)
Also in Petrolia
Amounts are federal dollars committed, not spent to date. Status is inferred from the dates above, not reported by the source. Project 24722 in the federal list. How to read these figures.