Rehabilitation of Hunter Street Bridge
Federal contribution
$4.4M
$4,357,318
Federal share33%
of $13.1M total eligible cost; the rest comes from other partners.
Schedule
Announced and approvedFeb 13, 2009
2009201120132015
Built
- Program
- Building Canada Fund - Communities Component
- Ultimate recipient
- City of Peterborough
- Construction start
- Apr 1, 2010(actual)
- Construction end
- Dec 31, 2015(actual)
Against the original forecast
- Construction start10 months lateforecast May 25, 2009
- Construction end3 months earlyforecast Mar 31, 2016
Also in Peterborough
Amounts are federal dollars committed, not spent to date. Status is inferred from the dates above, not reported by the source. Project 24723 in the federal list. How to read these figures.