Replacement of the Trout Creek Bridge #009013
Federal contribution
$303,829
Federal share33%
of $911.5K total eligible cost; the rest comes from other partners.
Schedule
Announced and approvedFeb 13, 2009
Built
- Program
- Building Canada Fund - Communities Component
- Ultimate recipient
- County of Perth
- Construction start
- Jul 13, 2009(actual)
- Construction end
- Oct 30, 2009(actual)
Also in Stratford