Construction of Salt Storage Facilities
Federal contribution
$1.9M
$1,850,000
Federal share33%
of $5.5M total eligible cost; the rest comes from other partners.
Schedule
Announced and approvedFeb 13, 2009
20102011
Built
- Program
- Building Canada Fund - Communities Component
- Ultimate recipient
- Stormont, Dundas and Glengarry, United Counties of
- Construction start
- Sep 1, 2009(actual)
- Construction end
- Dec 31, 2010(actual)
Against the original forecast
- Construction start4 months lateforecast May 1, 2009
- Construction end2 months lateforecast Oct 31, 2010
Also in Cornwall
- Cornwall Wastewater Treatment$18.5M
- Construction of Cornwall Multi Sport Facility$9.2M
- Replacement Conventional and Para Transit Buses$4.8M
- Rehabilitation of Cast Iron Watermains on Water Street, Riverdale, and East End Neighbourhoods to improve structural and hydraulic performance.$1.7M
- New Emergency Medical Services Headquarters Building$1.7M
Amounts are federal dollars committed, not spent to date. Status is inferred from the dates above, not reported by the source. Project 24760 in the federal list. How to read these figures.