Rehabilitation of Cast Iron Watermains on Water Street, Riverdale, and East End Neighbourhoods to improve structural and hydraulic performance.

Cornwall, Ontario

completeDrinking WaterCWWF
Federal contribution
$1.7M
$1,686,793
Federal share50%

of $3.4M total eligible cost; the rest comes from other partners.

Schedule

Announced and approvedMay 23, 2017
2018
Built

Approved 2 weeks before the announcement.

Program
Clean Water and Wastewater Fund
Ultimate recipient
City of Cornwall
Construction start
Jun 15, 2017(actual)
Construction end
Nov 16, 2018(actual)

Against the original forecast

  • Construction start6 weeks lateforecast May 1, 2017
  • Construction end2 weeks earlyforecast Nov 30, 2018

Also in Cornwall

Amounts are federal dollars committed, not spent to date. Status is inferred from the dates above, not reported by the source. Project 48687 in the federal list. How to read these figures.