Back to projects

Rehabilitation of the South River Library

South River, Ontario

completeCultureCC
Federal contribution
$166,891
Federal share33%

of $500.7K total eligible cost; the rest comes from other partners.

Schedule

Announced and approvedFeb 13, 2009
2010
Built
Program
Building Canada Fund - Communities Component
Ultimate recipient
Village of South River
Construction start
Apr 1, 2009(actual)
Construction end
Jun 30, 2010(actual)

Against the original forecast

  • Construction end2 years earlyforecast Jul 3, 2012

Also in South River

Amounts are federal dollars committed, not spent to date. Status is inferred from the dates above, not reported by the source. Project 24787 in the federal list. How to read these figures.