Replacement of Watermains and Road Reconstruction
Federal contribution
$271,147
Federal share33%
of $813.4K total eligible cost; the rest comes from other partners.
Schedule
Announced and approvedJun 5, 2009
Built
- Program
- Building Canada Fund - Communities Component Top Up
- Ultimate recipient
- Village of South River
- Construction start
- Sep 8, 2009(actual)
- Construction end
- Nov 30, 2009(actual)
Also in South River