Back to projects

Edmonton Northlands Agricom Exhibition Facility Expansion

Edmonton, Alberta

completeTourismMIC
Federal contribution
$25.0M
$25,000,000
Federal share32%

of $77.5M total eligible cost; the rest comes from other partners.

Schedule

Announced and approvedAug 29, 2008
200920102011
Built

Approved 2 months before the announcement.

Program
Building Canada Fund - Major Infrastructure Component
Ultimate recipient
Edmonton Northlands
Construction start
Jul 15, 2008(actual)
Construction end
Jun 16, 2011(actual)