Development of a testing strategy for water and sewer systems
Federal contribution
$50,000
Federal share30%
of $166.6K total eligible cost; the rest comes from other partners.
Schedule
Announced and approvedMar 15, 2016
2009201120132015
Built
Approved 7.2 years before the announcement.
- Program
- Municipal Rural Infrastructure Fund
- Ultimate recipient
- City of Hull
- Construction start
- Jan 5, 2009(actual)
- Construction end
- Mar 31, 2012(actual)
Against the original forecast
- Construction end2.1 years lateforecast Mar 5, 2010
Also in Gatineau
Amounts are federal dollars committed, not spent to date. Status is inferred from the dates above, not reported by the source. Project 24808 in the federal list. How to read these figures.