Development of a testing strategy for water and sewer systems

Gatineau, Quebec

completeCapacity BuildingMRIF
Federal contribution
$50,000
Federal share30%

of $166.6K total eligible cost; the rest comes from other partners.

Schedule

Announced and approvedMar 15, 2016
2009201120132015
Built

Approved 7.2 years before the announcement.

Program
Municipal Rural Infrastructure Fund
Ultimate recipient
City of Hull
Construction start
Jan 5, 2009(actual)
Construction end
Mar 31, 2012(actual)

Against the original forecast

  • Construction end2.1 years lateforecast Mar 5, 2010

Also in Gatineau

Amounts are federal dollars committed, not spent to date. Status is inferred from the dates above, not reported by the source. Project 24808 in the federal list. How to read these figures.