Comparative study of the impact of compaction on two types of coating for underground facilities
Federal contribution
$47,322
Federal share29%
of $161.8K total eligible cost; the rest comes from other partners.
Schedule
Announced and approvedMar 15, 2016
2009201120132015
Built
Approved 7.2 years before the announcement.
- Program
- Municipal Rural Infrastructure Fund
- Ultimate recipient
- City of Dorval
- Construction start
- Jan 12, 2009(actual)
- Construction end
- Nov 23, 2009(actual)