Back to projects

Rehabilitation of water mains for Martin and Swallow avenues

Dorval, Quebec

completeDrinking WaterCC
Federal contribution
$110,137
Federal share33%

of $330.4K total eligible cost; the rest comes from other partners.

Schedule

Announced and approvedMar 15, 2016
2016
Built

Approved 9 months before the announcement.

Program
Building Canada Fund - Communities Component
Ultimate recipient
City of Dorval
Construction start
Sep 25, 2015(actual)
Construction end
Feb 23, 2016(actual)

Against the original forecast

  • Construction start5 months lateforecast May 4, 2015
  • Construction end6 months lateforecast Aug 28, 2015

Also in Dorval

Amounts are federal dollars committed, not spent to date. Status is inferred from the dates above, not reported by the source. Project 45912 in the federal list. How to read these figures.