Jasper Activity and Aquatic Centre Renovation

Jasper, Alberta

completeGreen EnergyCC
Federal contribution
$1.5M
$1,500,000
Federal share26%

of $5.7M total eligible cost; the rest comes from other partners.

Schedule

Announced and approvedJan 30, 2009
2009201020112012
Built
Program
Building Canada Fund - Communities Component
Ultimate recipient
Municipality of Jasper
Construction start
Mar 1, 2010(actual)
Construction end
Oct 4, 2012(actual)

Against the original forecast

  • Construction start10 months lateforecast May 1, 2009
  • Construction end2 years lateforecast Sep 30, 2010