Jasper Recreation Facilities Renovation and Upgrade

Jasper, Alberta

completeRecreationRNIS
Federal contribution
$3.7M
$3,664,584
Federal share40%

of $9.2M total eligible cost; the rest comes from other partners.

Schedule

Announced and approvedAug 25, 2020
20212022202320242025
Built

Approved 5 weeks before the announcement.

Program
Rural & Northern Infrastructure Stream
Ultimate recipient
Municipality of Jasper
Construction start
Aug 11, 2022(actual)
Construction end
Dec 17, 2024(actual)

Against the original forecast

  • Construction start7 months earlyforecast Mar 1, 2023
  • Construction end3 weeks earlyforecast Jan 7, 2025

Also in Jasper

Amounts are federal dollars committed, not spent to date. Status is inferred from the dates above, not reported by the source. Project 56655 in the federal list. How to read these figures.