Jasper Recreation Facilities Renovation and Upgrade
Federal contribution
$3.7M
$3,664,584
Federal share40%
of $9.2M total eligible cost; the rest comes from other partners.
Schedule
Announced and approvedAug 25, 2020
20212022202320242025
Built
Approved 5 weeks before the announcement.
- Program
- Rural & Northern Infrastructure Stream
- Ultimate recipient
- Municipality of Jasper
- Construction start
- Aug 11, 2022(actual)
- Construction end
- Dec 17, 2024(actual)
Against the original forecast
- Construction start7 months earlyforecast Mar 1, 2023
- Construction end3 weeks earlyforecast Jan 7, 2025
Also in Jasper
- Purchase of vehicles, e-bikes and supporting infrastructure to launch a transit system in Jasper, Alberta$5.0M
- Jasper Municipal Library Renovation & Expansion$1.5M
- Jasper Activity and Aquatic Centre Renovation$1.5M
- Public Transit Solution Plan for Jasper, Alberta$50.0K
- Promoting Active Transportation in Jasper$49.9K
Amounts are federal dollars committed, not spent to date. Status is inferred from the dates above, not reported by the source. Project 56655 in the federal list. How to read these figures.