Home Road Highway Commercial/Industrial Water & Sewer Development
Federal contribution
$749,372
Federal share33%
of $2.2M total eligible cost; the rest comes from other partners.
Schedule
AnnouncedJan 30, 2009
ApprovedSep 9, 2009
2009201020112012
Built
Approved 7 months after the announcement.
- Program
- Building Canada Fund - Communities Component
- Ultimate recipient
- Town of Rainbow Lake
- Construction start
- Jun 12, 2010(actual)
- Construction end
- Feb 2, 2012(actual)
Against the original forecast
- Construction end2.2 years earlyforecast Mar 31, 2014
Also in Rainbow Lake
Amounts are federal dollars committed, not spent to date. Status is inferred from the dates above, not reported by the source. Project 24876 in the federal list. How to read these figures.