Town of Rainbow Lake Water Distribution System Rehabilitation
Federal contribution
$700,000
Federal share33%
of $2.1M total eligible cost; the rest comes from other partners.
Schedule
Announced and approvedJul 31, 2015
201620172018201920202021
Built
- Program
- Provincial-Territorial Infrastructure Component - Small Communities Fund
- Ultimate recipient
- Town of Rainbow Lake
- Construction start
- Sep 1, 2015(actual)
- Construction end
- Sep 27, 2021(actual)
Against the original forecast
- Construction start4 weeks lateforecast Aug 1, 2015
- Construction end4 weeks lateforecast Sep 1, 2021