Water Treatment Plant Upgrade
Federal contribution
$3.0M
$3,000,000
Federal share31%
of $9.6M total eligible cost; the rest comes from other partners.
Schedule
Announced and approvedJan 30, 2009
2009201020112012
Built
- Program
- Building Canada Fund - Communities Component
- Ultimate recipient
- Town of Hinton
- Construction start
- Nov 1, 2009(actual)
- Construction end
- Dec 19, 2011(actual)
Against the original forecast
- Construction start6 months lateforecast May 1, 2009
- Construction end2.3 years earlyforecast Mar 31, 2014
Also in Hinton
Amounts are federal dollars committed, not spent to date. Status is inferred from the dates above, not reported by the source. Project 24881 in the federal list. How to read these figures.