Hinton-Maxwell Lake Bridge and Beaver Boardwalk Rehab and Repairs

Hinton, Alberta

completeActive TransportationCVRIS
Federal contribution
$251,144
Federal share78%

of $320.0K total eligible cost; the rest comes from other partners.

Schedule

Announced and approvedAug 10, 2021
20222023
Built

Approved 4 months before the announcement.

Program
COVID-19 Resilience Stream
Ultimate recipient
Town of Hinton
Construction start
Mar 21, 2023(actual)
Construction end
Apr 25, 2023(actual)

Against the original forecast

  • Construction start4 months lateforecast Nov 20, 2022
  • Construction end7 months earlyforecast Dec 1, 2023