Nisku Spine Road Construction - Phase 1
Federal contribution
$2.4M
$2,438,836
Federal share32%
of $7.5M total eligible cost; the rest comes from other partners.
Schedule
Announced and approvedJan 30, 2009
200920102011
Built
- Program
- Building Canada Fund - Communities Component
- Ultimate recipient
- County of Leduc
- Construction start
- May 31, 2009(actual)
- Construction end
- Nov 14, 2011(actual)
Against the original forecast
- Construction start6 weeks earlyforecast Jul 15, 2009
- Construction end15 months lateforecast Aug 15, 2010