Nisku Road Reconstruction
Federal contribution
$2.0M
$1,951,931
Federal share33%
of $5.9M total eligible cost; the rest comes from other partners.
Schedule
Announced and approvedMay 21, 2009
2010201120122013
Built
- Program
- Building Canada Fund - Communities Component
- Ultimate recipient
- County of Leduc
- Construction start
- May 1, 2010(actual)
- Construction end
- Nov 29, 2012(actual)
Against the original forecast
- Construction end12 months lateforecast Nov 30, 2011
Also in Nisku
Amounts are federal dollars committed, not spent to date. Status is inferred from the dates above, not reported by the source. Project 24980 in the federal list. How to read these figures.