Nisku Road Reconstruction

Nisku, Alberta

completeHighways and RoadsCC
Federal contribution
$2.0M
$1,951,931
Federal share33%

of $5.9M total eligible cost; the rest comes from other partners.

Schedule

Announced and approvedMay 21, 2009
2010201120122013
Built
Program
Building Canada Fund - Communities Component
Ultimate recipient
County of Leduc
Construction start
May 1, 2010(actual)
Construction end
Nov 29, 2012(actual)

Against the original forecast

  • Construction end12 months lateforecast Nov 30, 2011