LaCrete 100 Ave and 102 Street Improvements

Fort Vermilion, Alberta

completeHighways and RoadsCC
Federal contribution
$288,971
Federal share33%

of $866.9K total eligible cost; the rest comes from other partners.

Schedule

Announced and approvedJan 30, 2009
20092010
Built

Approved 2 weeks before the announcement.

Program
Building Canada Fund - Communities Component
Ultimate recipient
County of Mackenzie
Construction start
Jul 1, 2010(actual)
Construction end
Oct 18, 2010(actual)

Against the original forecast

  • Construction start15 months lateforecast Apr 1, 2009
  • Construction end7 weeks lateforecast Sep 1, 2010