Hamlet of Fort Vermilion River Road Reconstruction

Fort Vermilion, Alberta

completeHighways and RoadsCC Top Up
Federal contribution
$357,223
Federal share33%

of $1.1M total eligible cost; the rest comes from other partners.

Schedule

Announced and approvedMay 21, 2009
2010
Built
Program
Building Canada Fund - Communities Component Top Up
Ultimate recipient
County of Mackenzie
Construction start
Jun 25, 2009(actual)
Construction end
Nov 22, 2010(actual)

Against the original forecast

  • Construction start3 weeks lateforecast Jun 1, 2009
  • Construction end11 months lateforecast Dec 31, 2009

Also in Fort Vermilion

Amounts are federal dollars committed, not spent to date. Status is inferred from the dates above, not reported by the source. Project 25262 in the federal list. How to read these figures.