Kleefeld Waste Water Treatment Facility
Federal contribution
$234,536
Federal share30%
of $793.8K total eligible cost; the rest comes from other partners.
Schedule
Announced and approvedMay 1, 2009
Built
- Program
- Building Canada Fund - Communities Component Top Up
- Ultimate recipient
- Rural Municipality of Hanover
- Construction start
- Aug 4, 2009(actual)
- Construction end
- Oct 28, 2009(actual)
Also in Steinbach