Souris Wastewater Treatment Plant

Souris-Glenwood, Manitoba

completeWastewaterCC Top Up
Federal contribution
$300,667
Federal share33%

of $902.0K total eligible cost; the rest comes from other partners.

Schedule

Announced and approvedMay 1, 2009
20102011
Built
Program
Building Canada Fund - Communities Component Top Up
Ultimate recipient
Town of Souris
Construction start
Jun 5, 2010(actual)
Construction end
Jun 30, 2011(actual)

Against the original forecast

  • Construction end4 weeks lateforecast May 31, 2011