Crescent Ave Infrastructure Renewal

Souris-Glenwood, Manitoba

completeDrinking WaterSCF
Federal contribution
$500,000
Federal share33%

of $1.5M total eligible cost; the rest comes from other partners.

Schedule

Announced and approvedAug 9, 2017
2018201920202021
Built

Approved 4 weeks before the announcement.

Program
Provincial-Territorial Infrastructure Component - Small Communities Fund
Construction start
May 21, 2019(actual)
Construction end
Jan 22, 2021(actual)

Against the original forecast

  • Construction start18 months lateforecast Nov 6, 2017
  • Construction end10 months lateforecast Mar 31, 2020