Crescent Ave Infrastructure Renewal
Federal contribution
$500,000
Federal share33%
of $1.5M total eligible cost; the rest comes from other partners.
Schedule
Announced and approvedAug 9, 2017
2018201920202021
Built
Approved 4 weeks before the announcement.
- Program
- Provincial-Territorial Infrastructure Component - Small Communities Fund
- Ultimate recipient
- Rural Municipality of Souris-Glenwood
- Construction start
- May 21, 2019(actual)
- Construction end
- Jan 22, 2021(actual)
Against the original forecast
- Construction start18 months lateforecast Nov 6, 2017
- Construction end10 months lateforecast Mar 31, 2020
Also in Souris-Glenwood
Amounts are federal dollars committed, not spent to date. Status is inferred from the dates above, not reported by the source. Project 51620 in the federal list. How to read these figures.