Lorette Water Upgrade -Phase 2

Lorette, Manitoba

completeDrinking WaterCC Top Up
Federal contribution
$600,000
Federal share33%

of $1.8M total eligible cost; the rest comes from other partners.

Schedule

Announced and approvedMay 1, 2009
2010
Built
Program
Building Canada Fund - Communities Component Top Up
Construction start
Jun 15, 2009(actual)
Construction end
May 14, 2010(actual)

Against the original forecast

  • Construction end4 weeks earlyforecast Jun 10, 2010

Also in Lorette