Lorette Lagoon Expansion & Nutrient Removal

Lorette, Manitoba

completeWastewaterCC
Federal contribution
$800,000
Federal share33%

of $2.4M total eligible cost; the rest comes from other partners.

Schedule

Announced and approvedMar 15, 2016
20162017
Built

Approved 9 months before the announcement.

Program
Building Canada Fund - Communities Component
Construction start
Jun 16, 2015(actual)
Construction end
Jan 13, 2017(actual)

Against the original forecast

  • Construction end12 months lateforecast Dec 31, 2015

Also in Lorette

Amounts are federal dollars committed, not spent to date. Status is inferred from the dates above, not reported by the source. Project 46088 in the federal list. How to read these figures.