Lorette Lagoon Expansion & Nutrient Removal
Federal contribution
$800,000
Federal share33%
of $2.4M total eligible cost; the rest comes from other partners.
Schedule
Announced and approvedMar 15, 2016
20162017
Built
Approved 9 months before the announcement.
- Program
- Building Canada Fund - Communities Component
- Ultimate recipient
- Rural Municipality of Taché
- Construction start
- Jun 16, 2015(actual)
- Construction end
- Jan 13, 2017(actual)
Against the original forecast
- Construction end12 months lateforecast Dec 31, 2015
Also in Lorette
Amounts are federal dollars committed, not spent to date. Status is inferred from the dates above, not reported by the source. Project 46088 in the federal list. How to read these figures.