Schedule

Announced and approvedMay 1, 2009
201020112012201320142015
Built
Program
Building Canada Fund - Communities Component
Construction start
Jun 1, 2013(actual)
Construction end
Feb 20, 2015(actual)

Against the original forecast

  • Construction start4 weeks earlyforecast Jun 28, 2013
  • Construction end15 months lateforecast Dec 1, 2013