Pine Dock Water Treatment Plant

Pine Dock, Manitoba

completeDrinking WaterCC
Federal contribution
$240,940
Federal share23%

of $1.0M total eligible cost; the rest comes from other partners.

Schedule

Announced and approvedMay 1, 2009
20102011201220132014
Built
Program
Building Canada Fund - Communities Component
Construction start
Aug 1, 2012(actual)
Construction end
Apr 1, 2014(actual)

Against the original forecast

  • Construction end9 months lateforecast Jul 1, 2013