Water Plant Upgrade

Berwyn, Alberta

completeDrinking WaterCC
Federal contribution
$104,129
Federal share33%

of $312.4K total eligible cost; the rest comes from other partners.

Schedule

Announced and approvedMay 21, 2009
20102011
Built
Program
Building Canada Fund - Communities Component
Ultimate recipient
Village of Berwyn
Construction start
May 23, 2011(actual)
Construction end
Nov 7, 2011(actual)

Against the original forecast

  • Construction start23 months lateforecast Jul 1, 2009
  • Construction end22 months lateforecast Dec 31, 2009