Treated Water Reservoir and Pumphouse Upgrade

Berwyn, Alberta

completeDrinking WaterCWWF
Federal contribution
$139,000
Federal share50%

of $278.0K total eligible cost; the rest comes from other partners.

Schedule

Announced and approvedJul 6, 2017
2018
Built

Approved 5 weeks before the announcement.

Program
Clean Water and Wastewater Fund
Ultimate recipient
Village of Berwyn
Construction start
Jun 1, 2018(actual)
Construction end
Nov 30, 2018(actual)

Against the original forecast

  • Construction start4 weeks lateforecast May 1, 2018
  • Construction end4 months earlyforecast Mar 31, 2019

Also in Berwyn

Amounts are federal dollars committed, not spent to date. Status is inferred from the dates above, not reported by the source. Project 49911 in the federal list. How to read these figures.