Treated Water Reservoir and Pumphouse Upgrade
Federal contribution
$139,000
Federal share50%
of $278.0K total eligible cost; the rest comes from other partners.
Schedule
Announced and approvedJul 6, 2017
2018
Built
Approved 5 weeks before the announcement.
- Program
- Clean Water and Wastewater Fund
- Ultimate recipient
- Village of Berwyn
- Construction start
- Jun 1, 2018(actual)
- Construction end
- Nov 30, 2018(actual)
Against the original forecast
- Construction start4 weeks lateforecast May 1, 2018
- Construction end4 months earlyforecast Mar 31, 2019
Also in Berwyn
Amounts are federal dollars committed, not spent to date. Status is inferred from the dates above, not reported by the source. Project 49911 in the federal list. How to read these figures.