Underground Utilidor
Norman Wells, Northwest Territories
Federal contribution
$219,599
Federal share15%
of $1.5M total eligible cost; the rest comes from other partners.
Schedule
Announced and approvedMar 15, 2016
2009201120132015
Built
Approved 7 years before the announcement.
- Program
- Municipal Rural Infrastructure Fund
- Ultimate recipient
- Town of Norman Wells
- Construction start
- Jul 6, 2009(actual)
- Construction end
- Mar 21, 2012(actual)
Against the original forecast
- Construction end2.4 years lateforecast Oct 30, 2009