Back to projects

Underground Utilidor

Norman Wells, Northwest Territories

completeDrinking WaterMRIF
Federal contribution
$219,599
Federal share15%

of $1.5M total eligible cost; the rest comes from other partners.

Schedule

Announced and approvedMar 15, 2016
2009201120132015
Built

Approved 7 years before the announcement.

Program
Municipal Rural Infrastructure Fund
Ultimate recipient
Town of Norman Wells
Construction start
Jul 6, 2009(actual)
Construction end
Mar 21, 2012(actual)

Against the original forecast

  • Construction end2.4 years lateforecast Oct 30, 2009

Also in Norman Wells

Amounts are federal dollars committed, not spent to date. Status is inferred from the dates above, not reported by the source. Project 25780 in the federal list. How to read these figures.