Paintearth Regional Reservoir
Federal contribution
$3.0M
$3,000,000
Federal share31%
of $9.6M total eligible cost; the rest comes from other partners.
Schedule
Announced and approvedMay 21, 2009
20102011
Built
- Program
- Building Canada Fund - Communities Component Top Up
- Ultimate recipient
- County of Paintearth No. 18
- Construction start
- Apr 21, 2010(actual)
- Construction end
- Oct 31, 2011(actual)
Against the original forecast
- Construction start3 weeks lateforecast Apr 1, 2010
- Construction end11 months lateforecast Dec 1, 2010