Town of Castor - Water, Wastewater, Storm Revitalization Program
Federal contribution
$1.3M
$1,315,100
Federal share33%
of $3.9M total eligible cost; the rest comes from other partners.
Schedule
Announced and approvedJul 31, 2015
201620172018
Built
- Program
- Provincial-Territorial Infrastructure Component - Small Communities Fund
- Ultimate recipient
- Town of Castor
- Construction start
- Jun 1, 2016(actual)
- Construction end
- Aug 27, 2018(actual)
Against the original forecast
- Construction start4 weeks lateforecast May 1, 2016
- Construction end5 weeks earlyforecast Oct 1, 2018
Also in Castor
Amounts are federal dollars committed, not spent to date. Status is inferred from the dates above, not reported by the source. Project 46313 in the federal list. How to read these figures.