Town of Eckville Lift Station and Forcemain Upgrades
Federal contribution
$546,898
Federal share33%
of $1.7M total eligible cost; the rest comes from other partners.
Schedule
Announced and approvedMay 21, 2009
20102011
Built
- Program
- Building Canada Fund - Communities Component Top Up
- Ultimate recipient
- Town of Eckville
- Construction start
- Sep 20, 2010(actual)
- Construction end
- Oct 24, 2011(actual)
Against the original forecast
- Construction start15 months lateforecast Jul 1, 2009
- Construction end14 months lateforecast Sep 1, 2010
Also in Eckville