Back to projects

Town of Eckville Lift Station and Forcemain Upgrades

Eckville, Alberta

completeWastewaterCC Top Up
Federal contribution
$546,898
Federal share33%

of $1.7M total eligible cost; the rest comes from other partners.

Schedule

Announced and approvedMay 21, 2009
20102011
Built
Program
Building Canada Fund - Communities Component Top Up
Ultimate recipient
Town of Eckville
Construction start
Sep 20, 2010(actual)
Construction end
Oct 24, 2011(actual)

Against the original forecast

  • Construction start15 months lateforecast Jul 1, 2009
  • Construction end14 months lateforecast Sep 1, 2010

Also in Eckville

Amounts are federal dollars committed, not spent to date. Status is inferred from the dates above, not reported by the source. Project 25878 in the federal list. How to read these figures.