Town of Eckville – Water Pump House and Reservoir Upgrades

Eckville, Alberta

completeDrinking WaterGIS
Federal contribution
$288,692
Federal share40%

of $721.7K total eligible cost; the rest comes from other partners.

Schedule

Announced and approvedAug 25, 2020
20212022
Built

Approved 3 months before the announcement.

Program
Green Infrastructure Stream
Ultimate recipient
Town of Eckville
Construction start
May 25, 2021(actual)
Construction end
Feb 11, 2022(actual)

Against the original forecast

  • Construction start3 weeks lateforecast May 3, 2021
  • Construction end2 months lateforecast Nov 30, 2021