Back to projects

Vernon - Road Improvements

Vernon, British Columbia

completeHighways and RoadsCC Top Up
Federal contribution
$972,221
Federal share31%

of $3.1M total eligible cost; the rest comes from other partners.

Schedule

Announced and approvedSep 24, 2009
20102011
Built
Program
Building Canada Fund - Communities Component Top Up
Ultimate recipient
City of Vernon
Construction start
May 11, 2010(actual)
Construction end
Oct 31, 2011(actual)

Also in Vernon