Highway 97 - Resurfacing
Federal contribution
$1.1M
$1,150,000
Federal share50%
of $2.3M total eligible cost; the rest comes from other partners.
Schedule
Announced and approvedNov 19, 2009
2010
Built
- Program
- Infrastructure Stimulus Fund
- Ultimate recipient
- Government of British Columbia
- Construction start
- Aug 3, 2010(actual)
- Construction end
- Sep 7, 2010(actual)
Against the original forecast
- Construction start4 weeks lateforecast Jul 5, 2010
- Construction end3 weeks earlyforecast Sep 30, 2010
Also in Vernon
Amounts are federal dollars committed, not spent to date. Status is inferred from the dates above, not reported by the source. Project 39396 in the federal list. How to read these figures.