50 Street Rehabilitation - Town of Ponoka
Federal contribution
$842,533
Federal share30%
of $2.8M total eligible cost; the rest comes from other partners.
Schedule
Announced and approvedMay 21, 2009
20102011
Built
- Program
- Building Canada Fund - Communities Component
- Ultimate recipient
- Town of Ponoka
- Construction start
- May 11, 2010(actual)
- Construction end
- Oct 31, 2011(actual)
Against the original forecast
- Construction start12 months lateforecast May 25, 2009