Expansion of the Ponoka Lagoon

Ponoka, Alberta

completeWastewaterISF
Federal contribution
$144,756
Federal share27%

of $539.3K total eligible cost; the rest comes from other partners.

Schedule

AnnouncedJul 9, 2009
ApprovedJul 23, 2010
20102011
Built

Approved 12 months after the announcement.

Program
Infrastructure Stimulus Fund
Ultimate recipient
Town of Ponoka
Construction start
Oct 20, 2009(actual)
Construction end
Feb 1, 2011(actual)

Against the original forecast

  • Construction start6 weeks earlyforecast Dec 1, 2009
  • Construction end8 weeks earlyforecast Mar 31, 2011