Selkirk Water Service Area Rural Water Distribution System
Federal contribution
$3.0M
$3,000,000
Federal share30%
of $9.9M total eligible cost; the rest comes from other partners.
Schedule
Announced and approvedMay 21, 2009
20102011
Built
- Program
- Building Canada Fund - Communities Component
- Ultimate recipient
- County of Kneehill
- Construction start
- Mar 1, 2010(actual)
- Construction end
- Jun 8, 2011(actual)
Against the original forecast
- Construction start2 months earlyforecast May 1, 2010
- Construction end7 months lateforecast Oct 29, 2010
Also in Three Hills